Payment Terms That Protect You: Deposits, Progress Schedules, Retention, and Lien Rights
Deposit sizing by job type (including state caps), milestone-based progress schedules, retention math, late-fee enforcement, and mechanics lien preliminary notice compliance.
Profitable contractors go out of business on cash flow. Your payment terms are the biggest lever — bigger than any cost cut.
Cash flow is oxygen
Profitable contractors can still go out of business. The mechanism is almost always cash flow: a run of jobs where customer payments arrive slower than payroll, supplier invoices, and vehicle payments need to go out. Your payment terms are the single most important cash-flow lever — far more impactful than bookkeeping discipline or cost-cutting.
Good payment terms do three things: they get deposit money in before material costs go out, they pace progress payments with labor draws, and they leave a small retention at the end so you're motivated to do the punch list.
Deposit sizing
Deposit expectations vary by trade, job size, and market. 2026 industry norms:
| Job type | Typical deposit | When due |
|---|---|---|
| Service call (repair under $1,500) | None; full payment on completion | At service |
| Mid-size repair ($1,500–$5,000) | 25–33% | At signing |
| Remodel project ($5,000–$50,000) | 25–35% | At signing |
| New construction ($50,000+) | 10–20% | At signing |
| Cabinet / appliance jobs (long lead) | 50% at order, 50% at install | At signing |
Regulatory check: several states cap deposits on residential contracts at 10% or $1,000 (whichever is less), including California. Know your state's rule before accepting a 25% deposit on a $50,000 job — it may not be enforceable.
Progress payment schedule
Progress payments keep the job's cash flow in balance. The schedule should match major labor and material milestones, not calendar intervals. Example schedule for a $72,000 kitchen remodel (8-week project):
| Milestone | % of contract | Amount | Typical timing |
|---|---|---|---|
| Signing (deposit) | 20% | $14,400 | Day 0 |
| Demo + rough-in complete | 25% | $18,000 | Week 2 |
| Cabinets delivered and installed | 25% | $18,000 | Week 6 |
| Counters + appliances installed | 20% | $14,400 | Week 7 |
| Punch list complete + final walkthrough | 10% | $7,200 | Week 8 |
Structure it so you're not fronting your own payroll. Cash out should roughly track cash in — not ahead, not behind.
Retention (the final 10%)
The final 5–10% of a contract is traditionally “retention” or “retainage” — held by the customer until punch list is complete and final inspection passes. This exists because:
- It gives you motivation to finish well. The final payment drives punch-list attention.
- It gives the customer recourse. If something genuinely isn't right, they have a small pool of money to negotiate with.
- It's industry-standard — customers often refuse to pay 100% on completion because they've been told to hold back.
5–10% is the norm. Above 10%, you're subsidizing the customer; below 5%, customers feel you don't care about finish quality. The retention should be explicitly timed: “released within 7 days of written punch-list acceptance, not to exceed 30 days from substantial completion.”
Accepted payment methods and processing fees
Your contract should specify accepted methods. 2026 standard options:
- ACH / bank transfer: preferred for large payments — 0–0.8% processing fee, 1–2 day clearance
- Check: still common, especially older homeowners — allow 5 business days to clear before marking paid
- Credit card: accepted but surcharge the 2.9% processing fee back to the customer. On a $20,000 progress payment, absorbing 2.9% is $580 of margin given away
- Financing (Synchrony, Wisetack, GreenSky): useful close tool, but dealer fee is 3–10% depending on term; decide whether you absorb or pass through
- Wire transfer: rare residential; customer pays the $25–$35 wire fee
Handling late payments
Your contract should specify what happens when a payment is late:
- Grace period: typically 5 business days from invoice due date
- Late fee: 1.5% per month (18% APR) is standard and enforceable in most states; some states cap lower
- Stop-work clause: “if a progress payment is more than 10 business days past due, contractor may suspend work until payment is received, and the schedule will extend accordingly.” Protects both parties — customer knows the rule; you get schedule relief when you pause
- Mechanics lien preliminary notice: in states that require it (California, Texas, Oregon, and others), send the pre-lien at the start of the job. This isn't hostile; it's how the mechanics lien system works
Mechanics liens — your last-resort leverage
A mechanics lien is a legal claim against the property for unpaid work. It's your ultimate enforcement mechanism when a customer refuses to pay. Rules vary wildly by state:
- Preliminary notice deadline: some states require a pre-lien notice within 20 days of first work; missing the deadline waives your lien rights on that job
- Lien filing deadline: typically 60–180 days after last work; varies by state
- Foreclosure deadline: after filing, you generally have 90 days to 1 year to foreclose or the lien expires
- Waiver forms: conditional waivers (on payment) and unconditional waivers (payment received) are separate — use conditional until the check clears
Know your state. A compliance calendar of preliminary notices is one of the highest-ROI admin tasks in a contracting business.
Payment terms mistakes
- Too-small deposit. If your deposit doesn't cover initial material outlay, you're financing the customer's project with your credit line.
- Calendar-based progress payments. Tie to milestones, not dates. Weather and permits disrupt calendars.
- No late fee or stop-work clause. Customers pay late when there's no cost to doing so.
- Skipping preliminary lien notices. Missed deadlines waive your most powerful enforcement tool.
- Absorbing credit-card fees. On large transactions, 2.9% becomes real money. Pass the surcharge through where legal.
Frequently asked questions
- How much deposit should I collect on a remodel?
- 25–35% is industry standard for remodel projects in 2026, due at signing. New construction runs 10–20% because project totals are higher. Long-lead cabinet/appliance jobs often use 50% at order / 50% at install. Important: several states (including California) cap residential deposits at 10% or $1,000 — know your state's rule before quoting 25% on a $50k job.
- What's a fair progress payment schedule?
- Tie payments to milestones, not calendar dates. A typical 8-week kitchen remodel: 20% deposit, 25% at demo + rough-in complete, 25% at cabinet install, 20% at counters + appliances, 10% at punch-list acceptance. Structure so cash-out roughly tracks cash-in — not ahead, not behind.
- How much retention should I hold at the end of a job?
- 5–10% is standard retention. It gives you motivation to finish punch list well and gives the customer small negotiating leverage if something isn't right. Spell out the release: 'within 7 days of written punch-list acceptance, not to exceed 30 days from substantial completion.' Above 10% you're subsidizing the customer; below 5% you're signaling you don't care about finish work.
- What late fee can I charge on overdue payments?
- 1.5% per month (18% APR) is standard and enforceable in most states; a few cap lower. Include a grace period (typically 5 business days) and a stop-work clause: if payment is more than 10 business days past due, you may suspend work with schedule extension. These protect both sides — customer knows the rule, you get schedule relief.
- Should I file a mechanics lien on unpaid work?
- As a last resort, yes — but the enabling step is the preliminary notice (pre-lien) filed at the start of the job in states that require it (California, Texas, Oregon, etc.). Miss the deadline and you waive lien rights. Track preliminary notice deadlines as a recurring admin task; it's the highest-ROI compliance work in a contracting business.
One contractor business insight per week
Real pricing, sales, and ops breakdowns. No fluff. Unsubscribe anytime.
Keep reading
Setting Your Hourly Shop Rate: Burdened Labor, Overhead, and Target Profit Math
The full shop-rate formula — burdened labor + overhead per billable hour ÷ (1 − margin target). Worked example lands $130/hr; why 50% vs 75% billable utilization changes everything.
Read Business & OpsMaterial Markup Benchmarks by Trade: 2026 Multipliers, Home Depot Ceilings, and the Markup vs Margin Trap
Trade-by-trade markup multipliers from HVAC to landscape plants. Why 33% markup is only 25% margin, when the Home Depot ceiling kicks in, and how to price customer-supplied material.
Read Business & OpsChange Order Pricing Strategy: Why Verbal COs Kill Margin
Price change orders at a 15–30% labor premium, enforce signature-before-work, handle discovery with not-to-exceed ceilings, and set the expectation at the first walkthrough.
Read